2004-5 Pipe

 

Home

Projects

Background

2004 07 27 Heavy Rain

2004 08 30 Tropical Storm Gaston

Day 1 - Our Sandbox Toys are Bigger than Yours

Sandbox toys, day 3

Sandbox toys, day 4

Sandbox toys, 2004 12 22

Sandbox Toys, 2004 12 28

2004 12 29, More Cutting

2004 12 30 Second Cut, Headwall Starts

2005 01 03 Sandbox Toys

2005 01 04 Pipe Install

2005 01 05 Pipe Install

2005 01 06 Pipe Install

2005 01 07 Pipe Install

2005 01 10 Pipe Install

2005 01 11 Pipe Install

2005 01 12 Pipe Install

2005 01 13 Pipe Install

2005 01 17 Pipe Install, Last Sections

2005 01 18 Riprap In, Old Pipe Out

2005 01 19 Riprap In, Headwall Dig, Snow

2005 01 21 Headwall Pour Starts

2005 01 24 Headwall Forms Work

2005 01 25 Headwall Forms Work

2005 01 26 Headwall Forms Work, Headwall Poured

2005 01 27, Riprap, Drive Repaired

2005 01 28, Headwall Finished

2005 04 02 It Works

2005 04 15, Last Riprap, Grading

2005 04 18 Grout, Topsoil, Grading

2005 04 19 Topsoil, Grading, Grass

 

 

2005 01 17 Pipe Install, Last Sections

Prev Next

Today the last two sections of pipe went into the ground. This was at the "head" of the pipe, where the open stream that runs along our road goes underground.. Working at this end of the pipe was very sloppy. Part of this was due to the rain, but part of it is I think due to the old pipe having cracks. Water continually seeped out of the old pipe and the ground here was always saturated starting about 6 feet down. A real mess.

The weather was clear and very cold all day today. The low last night was in the teens, and the high was probably just a bit above freezing. IN the early morning the earth was frozen hard, but by mid morning it had been working into really nasty glop.


The first thing done was some digging, and then the trench box was moved. This next shows the excavator pushing the box along through the muck.

Some more digging for the pipe section shown.

Dropping it in..

Sealing the joints after getting it seated in gravel.

So digging for the second and last section can go in.

Pushing the box along again.

This is the muck that is coming out of the trench. It's nasty and smelly. It looked to me as if a dozen tyrannosauruses went out to eat and all had the same very bad brontosaurus for dinner..

The pipe is blocked with a large metal plate to keep it from filling up with rock and mud.

Once the digging is done they move the plate an inch so the water drains out, and then drop in a lot of gravel.

And the last section of pipe goes in!

And is seated in gravel.

And finally, some of the construction equipment and material leaves.

Tomorrow more digging for the headwall, and the riprap for the tail of the pipe should start to arrive.

Prev Next